CBS Broadcast Booth | Democratic National Convention | Boston MA
Architect: Bargmann Hendrie + Archetype | Boston, MA
Contract: $500,000

CBS Broadcast Booth: Elaine Construction was the Construction Manager for the fast track construction of the CBS Broadcast Booth at the 2004 Democratic National Convention held at the Fleet Center in Boston.

The high profile project had a two week construction schedule. The design incorporated state of the art broadcasting technologies for live broadcasting and television production capabilities. The project required the expertise of many trades and subcontractors all carefully and efficiently managed by of Elaine Construction's field staff.

 